Thursday, September 16, 2010

PROBLEM YANG DIJUMPAI SAAT MENGECEK ISOMETRIC DRAWINGS

Berikut ini saya coba untuk menginformasikan kepada anda masalah-masalah yang dihadapi pada saat mengecekan gambar isometric..tata cara ini saya peroleh dari teman yang bekerja di Fluor Daniel Inc.
Dan saya rasa ini sangat baik untuk kita yang ingin mendalami ilmu piping lebih lanjut.
Semua text dalam Bahasa Inggris dan kalau kurang paham dalam bahasa Inggris coba aja di translate lewat google translete.. http://www.google.com/

YOU ARE EXPECTED TO LEARN FROM THE MISTAKES OF OTHERS AND REDUCE THE NUMBER AND SERIOUSNESS OF MISTAKES ON ISOMETRICS BELOW IS A LIST OF TYPES OF "PROBLEMS" SEEN ON CHECKED ISOMETRICS FROM VARIOUS PROJECTS:

01 - Color code not used properly
02 - Data block not completely filed in
03 - Data block not checked
04 - Line continuation not checked
05 - Unrecognizable symbology

06 - Audit checklist not filled out completely or not filled out correctly
07 - Piping components that are incorrectly listed in the parts list categorizing them as
        shop, field, field assembly
08 - Field welds shown at every weld on a field fab iso
09 - Field welds omitted - especially at sheet continuations
10 - Checker made notes to self or others that were in red instead of black or blue
11 - Checker did not make himself clear in what was required, he used an ambiguous
        narrative statement rather than detailing and locating
12 - Steam trap piping checked without any standard or job instruction
13 - Impossible dimensions either PDS-generated or annotated - for example a gate valve
        6mm long
14 - Incompatability of piping components - for example a copper tee on a carbon steel
        header
15 - Pipe guides and their locations not checked
16 - Checker takes the time to write a note say ing a flow arrow is needed rather than just
        drawing it in red
17 - Vents and drains drawn in red but not located
18 - Dimensions changed for one millimeter
19 - High point vent specified as a sockolet and a screwed plug
20 - Unneeded field welds added by the checker
21 - Hydrostatic vents and drains missing
22 - Flanged valves added by the checker without locating dimensions
23 - Isometric checked with instrumentation on hold
24 - Duplication of dimensions by the checker - added to existing dimensions
25 - Piping components called out as required by the checker but not drawn or located
26 - Notes by the checker in red - "install drain", "clarify valve size and rating"
27 - Items added in parts list but not shown on the iso
28 - Checker added dimensions in red but also the word "approximate"
29 - Checker spent time correcting the quantities in the parts list

30 - Checker circled something in red with either the note "fix" or with a question mark
31 - Text is too small
32 - Screwed plug welded to valve
33 - Iso checked without stress sketch
34 - Mark numbers missing
35 - Checker marked up the parts list and nothing else
36 - Notes on the iso in black pencil that should be shown in red so the backdrafter will
        pick them up
37 - Checker is unsure if line is sloped (a note with a question mark)
38 - Parts list receiving more attention than the data block or graphic portion
39 - Steam/condensate break in the wrong place on a steam trap iso
40 - DUMB NOTE; "Reverse the flow" is written rather than drawing a red flow arrow
41 - An iso to be deleted is indicated as such with a post-it that can fall off instead of
       marking directly on the iso
42 - Lots of checker activity/marks in red on backcheck print
43 - Duplicating a red mark with a note saying EXACTLY the same thing
44 - Socketweld valve is field and needs FW on both ends of the valve
45 - Red question marks in the data block
46 - HOLD shown in black pencil
47 - 100mm long spoolpiece added between every place where fitting make up could be
        used
48 - A bend is shown but without a callout or radius
49 - Common BOP not called out at dummy supports
50 - Control valve manifold block valve and bypass not in proper location per jo standards.
51 - Lack of common sense...3 BA's in a configuration 2 meters long - two are sliding and
        one is fixed
52 - Steam trap piping that is not initially shown on the check print should be handled
       either by the checker drawing it in red or returning it to the designer to have it added for
       check - NOT just circle it up for the backdrafter to do
53 - Screwed gate valve has a plug welded to it

54 - Line needs future connection - checker says it's to be added but doesn't locate or
        detail it
55 - Line was checked without IDP being run
56 - Shoe has been deleted but the dimension remains in place
57 - FFW used on 1 1/2" pipe
58 - Expansion loop shown on a line not requiring stress analysis – IA header
59 - Field fab piping with mark numbers
60 - Steam trap at control valve manifold shown after the downstream block valve
61 - Modified support detail dimensions are mixed - some are in millimeters some are in
        inches
62 - Spec break shown at the weld of a weld neck flange
63 - Weep hole for relief valve to atm is in the side of the elbow
64 - The checker detailed rebar in a CPS
65 - Schedule of pipe being supported is called out on a support detail
66 - Check print already has been signed off - prior to check
67 - Header block valve is too far from the header
68 - Blow off valve missing at y-strainer
69 - Pipe is unsupported
70 - Horizontal line resting on a 5FS1S1 is u-bolted when it does not need a u-bolt
71 - Checking time for iso on audit status sheet says 5 minutes for a complex line
72 - Bolts and gaskets were removed from one sheet and were not added on the
        continuation sheet
73 - Pipe at minus 50 degrees but not requiring stress analysis
74 - Checker invented own library of symbols for audit status sheet - without explanation
75 - Bolt hole note stating industry standard is unnecessary
76 - Support detail shows insulation on the line, but the line is uninsulated
77 - 55 meters of straight pipe with out attachments of any kind are shop fabricated
78 - New dimension added in red, but old dimension is not deleted
        9 - 5G1 used on a line w/3" thick insulation - can't be done

80 - MISMATCH - audit checklist if for a different line number than the iso to which it is
        attached, yet the marks on the checklist match those on the iso
81 - Work point elevations at elbows and slope plus distance traveled do not "work" - can't
        be built
82 - Incomplete U-bolt call outs
83 - Weld dot shown on threaded connection
84 - Shop fab supports shown in field fab portion of parts list
85 - Galvanized, threaded pipe with galvanized malleable iron fittings shown as shop
        fabricated
86 - Undimensioned mark number
87 - Dimension locating shoe places one end of the shoe past the centerline of a nearby 90
       degree ell
88 - 5US used in a horizontal run. 5US used on galvanized pipe.
89 - Span charts not adhered to for proper support.
90 - Signing off iso's that have ERROR READING DATABASE on the parts list
91 - Elbow that is rotated but does not have the offset dimensionally called out.
92 - Insulation breaks that are unnecessary between header and vent.
93 - Incorrect item codes for pipe that is purchased pre-painted.
94 - Incorrect fab code for base supports and shoes.
95 - Carbon steel shoe on a stainless steel line. Putting shoes in the field that should go in
        the shop.
96 - Incorrect or no line continuation called out.
97 - Incorrect choice on PWHT / seal weld / fabrication category in the title box.
98 - Dimensions that can not be read.
99 - Not placing low point drains and high point vents on the shop portion of rack ISO's.
100- Noting PP for insulation for lines that do not require it.
101- Not maximizing spool piece sizes for shipping.
102- Placing field welds below platforms making welding more difficult than necessary.
103- Spool pieces that exceed shipping box size.

104- Checker spent time correcting "cut length" on bill of material.
105- Process drains left off.
106- PLSR not verified for completion.
107- Continuation at equipment not verified with latest nozzle report.
108- Not following standard for insulation lugs.
109- Incorrect call out for insulation lugs.
110- Not using coupling to join small bore pipe together.
111- Addition of couplings for pipe that is "T & C"
112- Not following assembly details for instruments.
113- Incorrect nipple length to get assembly outside of insulation.
114- Not sequencing P & I D with regard to branch location.
115- Handwheels not accessible.
116- Placing a FW in the middle of a pipe run (because of change of partition) rather than
         at a flange or fitting.
117- Breaking spec at the weld of a fitting rather than the valve.
118- Guides that are too close to a change of direction
119- Flow arrows on dummy supports and support stanchions.
120- Not meeting the minimum required size for dummy support.
121- Not utilizing bends in suitable locations where spec calls for them as PREFERRED
         FABRICATION"
122- Using short spool pieces that place welds too close together.
123- Incorrect boot size on the steam header.
124- Using 300# weld neck flanges instead of orifice flanges where required.
125- Adding a spool piece where high point vent could have been placed on the elbow
        (minimum from the weld).
126- Ignoring constructability issue when penetrating a platform.
127- Not giving enough clearance between insulation and grade.
128- Placing loose items like nipples in the shop
129- Making a FW at the large end of a reducer.

130- Creating pockets by using concentric reducers.
131- Not providing weep holes in tail pipes that vent to atmosphere.
132- Not showing dummy support on parts list.

No comments:

Post a Comment